Ten client websites moved from reseller hosting to a managed VPS to improve speed, control, and operational stability.

Ten client websites were running on reseller hosting with limited resources and control. The migration needed to preserve data while keeping disruption as short as possible.
Approach
- Inventoried domains, application versions, databases, email, DNS, and dependencies.
- Prepared the VPS, baseline hardening, web server, certificates, monitoring, and backups.
- Performed an initial copy followed by a final synchronisation to shorten the cutover window.
- Validated critical functions, forms, scheduled jobs, SSL, and email before changing DNS.
- Maintained a recovery plan for every migration stage.
Outcome
All websites moved into a more controlled environment. The team gained better resource visibility, documented configuration, and a clearer route for future capacity increases.